| Sindh Irrigation & Drainage Authority (SIDA) | |||||||||||
| (Social Mobilization Group Social Development Cell Transition Wing) | |||||||||||
| Status of trainings on "Contract Management & Environmental Management" to FOs selected for rehabilitation works under SOFWM Project and field staff | |||||||||||
| S # | Date | No of FOs | No. of participants | Venue | AWB | Project Year | Organizer of event | Remarks | |||
| 1st Training | 2nd Training | Farmers | Staff * | Total | |||||||
| 1 | June 06, 2005' | 6 | 0 | 13 | 19 | 32 | Mirpurkhas | NCAWB | 1st | PIAC / SMG | |
| 2 | September 24, 2005' | 10 | 0 | 35 | 8 | 43 | Badin | LBCAWB | 2nd | PIAC / SMG | |
| 3 | October 22, 2005' | 9 | 0 | 31 | 0 | 31 | Ghotki | GFCAWB | 2nd | PIAC /SMG | |
| 4 | June 27, 2006' | 2 | 5 | 31 | 4 | 35 | Matli | LBCAWB | 2nd | SMG SIDA | FOs having NCB contracts |
| 5 | June 28, 2006' | 1 | 5 | 24 | 8 | 32 | Matli | LBCAWB | 2nd | SMG SIDA | FOs having CBC contracts |
| 6 | July 15, 2006' | 0 | 0 | 0 | 32 | 32 | Hyderabad | SMG SIDA | TOT for SMG staff | ||
| 7 | October 31, 2006' | 6 | 0 | 12 | 19 | 31 | Mirpurkhas | NCAWB | 2nd | SMG SIDA | |
| 8 | January 22, 2007' | 10 | 0 | 35 | 5 | 40 | Sanghar | NCAWB | 3rd | SMG SIDA | |
| 9 | February 27, 2007' | 9 | 0 | 40 | 10 | 50 | Mirpurkhas | NCAWB | 3rd | SMG SIDA | |
| 10 | May 25, 2007' | 10 | 0 | 36 | 7 | 43 | Matli | LBCAWB | 3rd | SMG SIDA | |
| 11 | August 30, 2007' | 6 | 0 | 34 | 13 | 47 | Sanghar | NCAWB | 3rd | SMG SIDA | |
| 12 | February 09,2008 | 5 | 0 | 28 | 6 | 34 | Mirpurkhas | NCAWB | 3rd | SMG SIDA | |
| 13 | February 27, 2008' | 10 | 0 | 37 | 10 | 47 | Ghotki | GFCAWB | 3rd | SMG SIDA | |
| 14 | May 13, 2008' | 7 | 1 | 33 | 7 | 40 | Sanghar | NCAWB | 3rd & 4th | SMG SIDA | |
| Total | 91 | 11 | 389 | 148 | 537 | ||||||
| * The field staff of SMG - FMG - NDP reprograming Scheme SIDA, AWBs, WMO (SM) and PIA Consultants participated in training events organized at their field stations. | |||||||||||
| Habib Ahmedani | |||||||||||
| Training Coordinator | |||||||||||